>What You Missed at the Middletown Library Board’s June 15th Meeting

>by guest blogger Linda Baum

It was just me again Wednesday night, a little discouraged that more people didn’t show up to support the library. Anyway, here’s what you missed in those 3 hours.

First, an update on the $500K transfer. Scheduled for this meeting was final review of the strategic plan and annual report to be submitted to the State Librarian, plus a required second vote by the Board as to whether or not to proceed with the transfer.

The Board’s review of the budget forecast began with Ms. O’Neal pointing out the obvious, that library funding would be painfully low for years to come. Ms. Miloscia asked, since they would be giving up a lot, if the town would recognize that gesture in the future when the library needs assistance as well. Initially, this struck me as a silly question because I think the town committee has made it clear in which direction they expect money to flow. But it has since occurred to me the Board has a perfect right to know what the arrangement with the town will be. Committeeman Settembrino gave a well rehearsed response free of promises. He said that he didn’t see why not, but mentioned non-starters like the tax cap and the changing leadership on the committee (which will still be republican-controlled next year, by the way). And as evidence of the town’s concern for the library, he pointed out that the town’s 2012 capital improvement plan already includes them (under this plan, the town issues the debt and the library pays the debt service). Ms. O’Neal asked if the Board would be forced to proceed, and she may have meant proceed with the lot construction, the funding arrangement, or both. No to all. The Board has the option to pay cash outright for the work, which presumably would allow them to make their own arrangements except for having to use T&M as engineer. Ms. Miloscia asked, “What if we don’t have the money to pay for it?” Kevin replied, “[That] will be a discussion for next year’s committee, but at this point I would say it doesn’t get accomplished unless it’s funded in accordance with the resolution.” Translation: The Board has 2 options, to make payments on the debt or pay cash for the work, but they should not expect the town to pay for it. For now, the parking lot expansion is a dead issue.

If you read my last post, you know that at the May Board meeting, Ms. O’Neal mentioned that the Board had not been satisfied with prior work done by T&M, who has been sanctioned by the town committee as the one-and-only engineer for all library capital improvements. I asked about that – i.e., what work was done by T&M and when was it done? Only Ms. O’Neal and Mr. Gabrielan spoke and they declined to discuss it, saying it was long ago and they have been assured that T&M would do a fine job. Needless to say, everyone seemed acutely aware that Committeeman Settembrino was in the room. Susan glanced often in his direction as she spoke. Unfortunately, I couldn’t see what kind of looks were being exchanged because my view of Kevin was blocked by the sound equipment.

Review of the Board’s strategic goals led to a discussion about the library in Charlotte, North Carolina, which was at one time among the best funded professional-level libraries in the country, but which had to close branches following a loss of funding and the leadership of its long-time director.

The plight of the Charlotte Library demonstrates why improving library volunteerism is an important goal. Public advocacy – our time and our money – becomes increasingly important when political advocacy and funding fall short. Got some free time? Or college-bound and looking for community service credit? Contact your local library.

The strategic plan and annual report were unanimously adopted by a vote of 7-0 (Resolution 2011-32).

When it came time to vote on the transfer itself (Resolution 2011-33), only Board president Randy Gabrielan took the opportunity to condemn the self-serving, deceptive tactics used by the town committee and to voice his frustration with his fellow trustees. It deserves repeat here:

“We saw the evolving fiscal condition of the library in March and it is here in clear black and white in the strategic plan. We would be imperiling the fiscal well being of this library over the next couple of years if we gave this money away. As far as I personally am concerned, the giveaway is tantamount to the township committee declaring war on its own library. The whole process as I see it is one of the mayor seeking to fulfill his short term political goals, the mayor and the committee not having done what they could have done with respect to cap exceptions and an exemption to meet their budgetary requirements, and they are putting their obligations on us. They did it by various threats, including holding hostage police jobs. Then after we passed our preliminary resolution in March, they’re going to other meetings still holding the same jobs at risk. I was against this in March. I’m against it now. I would have strongly counseled that we rescind our prior passage and vote this down, but unfortunately on the advice of counsel, it seems that our hands are tied. …but I insist that if we as a body don’t recognize what this is doing to the financial well being of the library, that at least the record demonstrates that.”

There was a full 15 seconds of silence after that. It felt like a memorial.

“It’s too much water under the bridge at this point to undo what’s been done.…This Board made a commitment to the township to do this,” said Mr. Milne. There was tacit agreement, and a roomful of downcast eyes. After hearing from Ms. O’Neal that even the Board’s lawyers thought that the Board did not have good legal standing at this point to back off, it was clear that the pending vote was little more than a formality. Resolution 2011-33 passed 6-1, with only Mr. Gabrielan dissenting.

I have to wonder if the town committee knew early on that the effect of railroading the Library Board into what was initially billed as non-binding negotiation would be to obligate them legally. Think back to the February Board meeting when Committeeman Settembrino pressed for a resolution to arrive at a number. The Board passed that resolution because they thought there was no harm in talking….

So now the matter will be passed along to the State Librarian, Norma Blake, for review. I heard somewhere that it could take up to 45 days for her decision. That doesn’t jive with the town committee’s plan to finalize their 2011 budget in early July. I asked Committeeman Settembrino how they expected to do that if the State Librarian hadn’t yet approved the transfer. The Board agreed with his assessment that all the documents were in order and that a quick response was expected from the State. Unfortunately, in line with regulations, the State Librarian reviews only the current year’s finances. Thus it is expected that the library’s budget shortfall for subsequent years will be ignored.

I asked Mr. Settembrino how the town would plug the $500K budget hole in the unlikely event the transfer was disapproved. He replied that the library board meeting wasn’t the right forum for that discussion, but he did clarify that the 2.99% tax hike (he said 2.99, not 2.9) reflects the 2% maximum increase within the cap.

Other business discussed at the meeting is as follows:

There was a slideshow presented by Dennis Kowal Architects, who recently completed a feasibility study for the renovation of the Lincroft branch, originally a 2-room schoolhouse built in 1906. The presentation was so packed with photos and sketches that if you’ve never been to the Lincroft branch, you’ll feel like you have. You can view the slideshow by clicking HERE

The good news is that the original structure is sound and can therefore be renovated. There is also ample parking since an overflow lot was added not long back. The renovation would include lots of energy efficiency upgrades while retaining existing wood floors and original hardware. A drawing of the architect’s proposed design is attached to this post. It includes a charming outdoor plaza-lounge created by sandwiching the front walkway between an existing structure and a new addition that would house new ADA-compliant bathrooms and an entry foyer. There is also a magazine lounge, a quiet study area, a contained children’s room (draft-free and no more runaways), and a fireside reading area complete with a gas-burning fireplace. If you live in Lincroft, you are probably filled with a sense of longing right now.

The project would cost roughly $650,000, not including new furniture, security and communication systems, architectural fees, or renovation to the basement storage area (filled with old municipal and police records). Add it all up, and the project budget would need to be in the range of $800 to $900K. And a caveat that the final design could change based on location of underground lines (the architect could not obtain a copy of the property survey).

The renovation probably won’t happen anytime soon because library funds are low for reasons we are all well aware of. The project might qualify for a matching New Jersey Historic Trust grant, but there is stiff competition for these grants, and Mr. Gabrielan, who is town historian in addition to being Library Board president, feels that the chance of getting the grant is slim. No decision has been made yet about how to proceed. The topic is slated for further discussion next month.

Ms. Cavalier asked if they knew how much financial support could be expected from the community. Susan said that $713K was donated for the 2004 renovation of the main branch, but only a small part of that was from Lincroft residents, who may be much more inclined to help fund their local branch. So be on the lookout for fundraisers!

If you are concerned about donating for fear your dollars will end up in the hands of the town, don’t worry. The Board was very clear that Library Foundation money is protected and is not part of the $500K transfer.

You may recall from a prior post that the Lincroft branch has termite damage in the entryway and is believed to have asbestos in the walls as well as lead-based paint. The architect didn’t test for hazardous materials and cautioned the board that if testing for hazmats is done, there is a legal requirement to remediate in line with test results. Susan advised that all paintable surfaces in the Lincroft branch were painted with latex paint in the last decade, so the lead-based paint poses no immediate concern. As for the termites, damage is supposedly concentrated in trim moulding rather than structural beams. The Board opted to wait and address these issues as part of the renovation.

Congratulations to Library Director Susan O’Neal, who is the NJ Library Association’s president-elect for coming fiscal year. “This is both a high honor and an awesome responsibility,” to quote Mr. Gabrielan. Susan’s name will be engraved on one of the silver-toned pages of a book-shaped locket to mark her achievement. The locket, a heavy piece made of gold and faience (tin-glazed ceramic), is the badge of office for NJLA presidents. Susan noted that the locket is actually too heavy to comfortably wear and reasoned that it was designed for a time when ladies wore much heavier clothing. A picture and history of the locket may soon appear on the library’s website.

In accordance with the Conover Whitol Scholarship guidelines, two graduate students enrolled in Rutgers’ library science program will receive $900 each toward the September term. Congratulations to recipients Debra Bodofsky and Elizabeth Edwards. (Resolution 2011-34, 7-0)

The Library welcomes back college student Stephanie Chadwick, who worked at the library last summer and is being re-hired part time for this year’s busy summer season. As a trained page, she is a valuable addition who can “hit the ground running”. (Resolution 2011-31, 7-0)

There was a first-time-ever theft of petty cash recently from the library’s Bayshore branch. The thief scored a negligible amount, and a lock-box will be added to deter future attempts. Yet another sign of the times.

Another topic concerned bill payments that have been held up by town administrator Tony Mercantante. In one instance, the requisition was for the payment of registration fees for a June conference that would provide training for five library assistants at a cost of $100 per person. The payment delay resulted in the registration deadline being missed, so the individuals couldn’t attend and will have to wait a year for the next conference. In another case, payment was denied for food expenses as part of conference attendance by a member of the library’s IT staff. Tony said the town doesn’t reimburse for food. However, the Library does. The Board felt this was unwarranted interference with Library operations. Mr. Gabrielan pointed out that the costs in question are normal outlays for staff development, benefit the library, and have been approved and budgeted for by the Board. Ms. Cavalier wondered if the problem was just ignorance (her word, not mine) on the part of the administrator.

In an effort to address the delays, Susan has contacted Mr. Mercantante, who feels he is within his authority. About a year ago, per Susan, Tony began asking for a written explanation for requisitions over $1000, but Susan said that the voucher, which is attached to the requisition, already lists that information, so to write it again is a duplication of effort for her. She said, “Anything over $1000 he sits on.” Part of the problem, Susan said, is that no one from the town contacts her when there is a question about an expense, so it doesn’t get addressed until she calls the town after there has already been a long delay. She’s wondered if maybe the slowness has to do with cash flow……

This was all news to Kevin, who said he’d look into it.

41 Comments